According to Huaneng Hydropower's announcement, the company completed 126.932 billion kWh of power generation in 2025, a year-on-year increase of 13.32%. On-grid power generation was 125.858 billion kWh, a year-on-year increase of 13.36%. The main reasons for the year-on-year increase in power generation in 2025 are: first, the year-on-year increase in electricity demand, with power generation in Yunnan Province and for the West-to-East Power Transmission project increasing year-on-year; second, the full-capacity commissioning of TB Hydropower Station and Yingliangbao Hydropower Station, and a significant increase in new energy installed capacity, leading to a year-on-year increase in power generation; third, the Nuzhadu section of the Lancang River basin experienced 15% more water inflow year-on-year, and the company made every effort to generate power during the main flood season, effectively releasing hydropower storage.